单项选择题
Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
A.performance
B.process
C.product
D.object
点击查看答案&解析
相关考题
-
单项选择题
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
A.budget
B.plan
C.risk
D.contract -
单项选择题
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development -
单项选择题
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement