单项选择题
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter
点击查看答案&解析
相关考题
-
单项选择题
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the projects requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing -
单项选择题
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders -
单项选择题
The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone