单项选择题
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
点击查看答案&解析
相关考题
-
单项选择题
() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A.Project managers
B.Project team members
C.Sponsors
D.Project stakeholders -
单项选择题
The() defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone -
单项选择题
()means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure