单项选择题
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
点击查看答案&解析
相关考题
-
单项选择题
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing -
单项选择题
The () describes, in detail, the projects deliverables and the work required to create those deliverables.
A.project scope statement
B.project requirement
C.project charter
D.product specification -
单项选择题
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.project charter